Capital Projects

The Engineering Department has been implementing projects from the 2008-2012 Capital Improvement Program, in the area of public infrastructure (roads, utilities and drainage). The ever-increasing challenges of a thriving and growing community have necessitated improvements in all categories.
  1. ROADS
  2. Utilities
  3. Facilities
  4. Future
  5. Maps
Lanes.png Alma Drive Improvements
(Hedgcoxe to SH 121) 
Project Manager: Tim Porter

Montgomery Extension Montgomery Boulevard Extension
(Bethany to US 75)
Project Manager: Kevin Bates                 

  • Construction anticipated to be complete March 2016.
  • Portion of Montgomery Boulevard will be built by Developer
Ridgeview (Alma through Stacy) Ridgeview Drive, Phase 1
(Alma through Stacy)
Project Manager: Kevin Bates        
  • 4 lane divided roadway connecting existing 2 lane roadways
  • Construction completion anticipated Spring 2016
Stacy Road Stacy Road
(Greenville Ave to FM 1378)
Project Contact: Tim Porter
  • TxDOT project currently in design
  • Utility Relocations Underway
  • Construction Start - Anticipated Fall 2015       
US 75 US 75
(Spring Creek Pkwy to Collin County Line)
Project Contact: Chris Flanigan
Planning continues on this important roadway segment as the communities of Allen, Anna, Melissa, Fairview, McKinney and Plano look towards the ultimate improvement of this roadway, with 8 main lanes and HOV lanes. 

  • TxDOT project adding 2 additional lanes and ramp improvements.
  • Construction estimated to be complete January 2017